Production Control Dashboard
Operational status in 4 quadrants (sample data / pending items marked)
Production
On-time tracking
Active orders128
On-time deliveries88%
Detected delays6
Capacity used
72%
Avg lead time
3.4 d
Workforce
Pending timeclock data
Hours required today420 h
Hours available380 h
People on floor38 / 44
Timeclock hours (pending)
Planned overtime
32 h
Flow by department
WIP balance
DeptQueuedIn processStatus
Laser96Flowing
Punch1410Strained
Press Break128Strained
Welding2016Blocked
Finishing75Flowing
Shipping53Flowing
Long queues: Welding, Punch Clear queues within 2h
Today's blocks and shipments
Pending floor confirmation
Machine Punch-02 stopped
Tech ETA: 10:30Impact: 6 orders
Material shortage: 3mm steel
Supplier ETA: 14:00Impact: Laser/Welding
Urgent shipments today
SO-9188, SO-9210, SO-9213Priority: high
Timeclock hours (pending ingest)
Waiting for timeclock sync